Entergy breaks ground on 1.2GW hydrogen-capable CCGT plant in Texas
Entergy has officially broken ground on the Orange County Advanced Power Station (OCAPS)| a 1|215MW combined cycle plant that will be located near Bridge City| Texas.

US-based power company Entergy has officially broken ground on the Orange County Advanced Power Station (OCAPS), a 1,215MW combined cycle plant that will be located near Bridge City, Texas.
Nearly 200 people, including Texas Gov. Greg Abbott, attended a groundbreaking ceremony this week to celebrate the start of construction.
Located in one of the largest industrial regions in the country, the plant would have the initial capability to use up to 30% hydrogen by volume along with natural gas to generate power.
Mitsubishi Power is supplying the two M501JAC gas turbines, steam turbine, heat recovery steam generator and advanced control recovery system. The company said OCAPS would eventually work up to 100% hydrogen. Hydrogen produces zero carbon emissions when combusted as a fuel source for electric generation.
Have you read?
Rolls-Royce shows mtu fuel cell system is black-start capable
GE gas turbine to be part of 1GW Czech virtual power plant
A consortium of Mitsubishi Power, Sargent & Lundy and TIC—The Industrial Company will provide Entergy with engineering, procurement and construction (EPC) services to build the plant.
The expected total cost of the project is $1.2 billion, which includes the estimated costs of the generation facilities, transmission upgrades, contingency, allowance for funds used during construction and necessary regulatory expenses, among others.
The construction of OCAPS is expected to create nearly $1.8 billion in total economic activity in Southeast Texas.
Originally published on power-eng.com